Huang Center Video

The trucks have been rolling since the Spring of 2008 and progress on the Huang Center and the neighboring Nanotechnology Center has been apparent every day since. Check for regular updates and new pictures, including a live view through our Webcam.


May 29, 2009

We are still on track for a March ’10 substantial completion date. Most of the priority walls (non-glass) walls are installed and utility systems are well underway from the basement floor up through the third floor.

Past Updates

June 01, 2009

The exterior is close to fully enclosed; Plumbing has advanced substantially. | View»


May 29, 2009

New Aerial images show the Quad taking shape. | View»


April 6, 2009

The precast exterior walls are nearing completion. | View»


February 22, 2009

Aerial shots from earlier this winter of the Huang Center and the neighboring Nanotechnology Center. | View»


January 30, 2009

The steel erection for both the Huang and Nano Centers is now complete. | View»


November 07, 2008

The Nanotechnology Center’s sub-basement floor slab is currently being poured. | View»


October 27, 2008

Huang Center steel erection started October 6. The Nano Technology Center’s foundations and shotcrete walls are well underway | View»


October 20, 2008

The steel box boundary you see in the first picture is east of the western most atrium and goes up to the pavilion neck to the north. | View»


October 6, 2008

The workers standing on the structural steel in the last photo are at the arcade level between the Pavilion and Bar building. | View»


September 17, 2008

Initial basement slab-on-grade concrete pour that occurred at the end of last week. | View»